Design and more views..
Daily updates for May..
Daily updates for April..
This reminder will follow each daily update...this is your park...do not risk injury to yourself or damage to the surfaces..by entering the site...Please Stay Out...
back
enlarge
enlarge
enlarge
Tues 1st June....Rain...setting out the upper platform...building up the level towards the driveway..and marking out the curved bank...
enlarge
enlarge
enlarge

Wed 2nd June...Upper platform ready for concrete..showing curved bank's hight and shape...timber forms the corner..and a good long run up to nail your first rail....

 

enlarge
enlarge
enlarge
enlarge
enlarge
Thurs 3rd June..Despite the rain the setting out of the driveway side levels continue...assorted edges..and laying out the coping.....
enlarge
enlarge
enlarge
enlarge
enlarge
enlarge
Fri 4th June.. Retaining Wall finished to the hip corner..another level ready to fill.. and rolling the upper platform...
enlarge
enlarge
enlarge
enlarge
Sat 5th June..Back filling and rolling the hip corner..the first signs of the spine fill..driveway side layout getting clearer..the best run up to a stair set Glasgow has ever seen... and another birds eye view...
enlarge
enlarge
enlarge
enlarge
Mon 7th June..Hip corner filled...ready for marking out...and the attention to detail on the finished upper platform....
enlarge
enlarge
enlarge
Tues 8th June..The position of the step up and hubba ledge can be seen now this level is poured...and the A team fill..stir.. and level the hip platform...it's a well oiled machine....
enlarge
enlarge
enlarge
enlarge
enlarge
enlarge
Wed 9th June..Steel pegs are driven into the workings and the coping is welded into place..The spine gets a little higher..Excavating the curved bank..And the completed hip platform...
enlarge
enlarge
enlarge
enlarge
enlarge
Thurs 10th June....Foundations for the curved corner.. ...the second combination set and a big overview ....note the gathering water on the right...this will run free when that edge is finished...
enlarge
enlarge
enlarge
enlarge
Fri 11th June..The bank to corner has to support the driveway level so lots of reinforcement..and it's all downhill from here...
enlarge
enlarge
enlarge
Sat 12th June..Excavating the main set...and the spine gets another top up...
enlarge
enlarge
Mon 14th June..A bit late with the update today...an early morning skate demo..still it went well...now..where was I...Todays pics show the slow process of forming the reinforcement steel...and Div gets ready to skate with Tony Hawk...no really..!!
enlarge
enlarge
enlarge
Tues 15th June...Foundation for inner block at curved set.. steel for the main sets hubba's.. and the joiners handywork...
enlarge
enlarge
enlarge
enlarge
Wed 16th June..The timber boxes form moulds for the ledges and hold the steel grind edges in place as the concrete is poured in...the other pics show lots more steelwork....
enlarge
enlarge
enlarge
enlarge
Thurs 17th June..Shuttering the curved set inner block...the first hubba with steel edges in place..and an overview..
enlarge
enlarge
enlarge
enlarge
Fri 18th June..The spine rises..the inner block is poured and edged...the driveway saddle will be a bank to wall on this side..and a full overview..I missed a corner yesterday...A big thanks to the boys for making me welcome on site every day...
enlarge
enlarge
enlarge
enlarge
Sat 19th June..Shuttering the driveway saddle...The skill of the machine operator in fine tuning the transitions is truely impressive..and look Charlie...it's your Dad...
June.. A look back at the projects third month..
enlarge
enlarge
enlarge
Mon 21st June..More timber..the saddle's steel..the first hubba...and the inner block...
enlarge
enlarge
enlarge
enlarge
enlarge
enlarge
enlarge
Tues 22nd June..feast your eyes...
enlarge
enlarge
enlarge
Wed 23rd June..Scottish summer..a fantastic day yesterday..a shit day today...still the bowl side ledges see the light of day...and the spine gets it's coping...
enlarge
enlarge
enlarge
Thurs 24th June..Despite the rain the work continues..shuttering the last ledge..the first flat bank.. and the transition steel...
enlarge
enlarge
enlarge
enlarge
Fri 25th June..More timber work..starting the stairs..fixing the steel edge..and even though you don't see it the mesh has to be right...
enlarge
enlarge
Sat 26th June.. Overcast..a dull day..yet more timber..and fine tuning the junction between flat bank and transition...
enlarge
enlarge
enlarge
enlarge
Mon 28th June.. The first step..the first flat bank..steel in place for the second bank..and working the level on the last side...
enlarge
enlarge
enlarge
enlarge
enlarge
enlarge
Tues 29th June...The first flat bank..the last ledge..filling the second bank..the driveway top..the first section of the curved wall..and altering the bowl base..
enlarge
enlarge
Wed 30th June..The change in the weather over the last few days brings it's own problems..but still there is progress every day..yesterdays wet concrete is todays flat bank..and the curved corner gets it's ledge....another fantastic months work..well done boys...
Daily updates for July/August..
enlarge